隧道联络通道冻结法施工三维有限元温度场分析

靳巍巍1,陈有亮2,李磊1,王灵敏3   

  1. 1.上海大学 土木工程系,上海 200072;
    2.上海理工大学 城建学院,上海 200093;
    3.中煤特殊凿井集团有限公司 上海分公司,上海 200135
  • 收稿日期:2006-10-23 修回日期:1900-01-01 出版日期:2008-02-28 发布日期:2008-02-28
  • 通讯作者: 陈有亮

FEM Analysis of 3D Temperature Field in Connection Aisle between Tunnels Constructed Using Artificial Freezing Method

JIN Wei-wei1, CHEN You-liang2, LI Lei1, WANG Ling-min3   

  1. 1. Department of Civil Engineering, Shanghai University, Shanghai 200072, China;
    2. College of Urban Construction and Environmental Engineering, University of Shanghai for Science and Technology, Shanghai 200093, China;
    3. Shanghai Branch of China Coal Special Project Ltd., Shanghai 200135, China
  • Received:2006-10-23 Revised:1900-01-01 Online:2008-02-28 Published:2008-02-28
  • Contact: CHEN You-liang

摘要: 人工冻结法是一种经济可靠的隧道联络通道开挖方法.在冻结法施工过程中,冻结壁厚度是否达到设计要求是安全施工的重要保证.该文考虑了实际施工过程中冻结管偏斜布置的情况,利用三维有限元方法对上海复兴东路越江隧道联络通道进行温度场模拟.针对单排冻结管和双排冻结管,分别在冻结壁底部、中部和顶部建立路径,绘制每条路径的温度分布曲线,查看不同路径处冻结壁厚度及其随时间发展变化情况,得出有意义的结论,对联络通道安全施工有重要参考价值.

关键词: 冻结壁, 联络通道, 人工冻结法, 三维有限元

Abstract: Artificial freezing method is an economical and effective method for digging connection aisles between tunnels. During the freezing, whether or not the wall reaches the designed thickness is important for safe construction. In this paper, the temperature field in the connection aisle of Shanghai East-Fuxing Road tunnels is computed using 3D FEM. The inclined installation of freezing tubes is taken into account in the computation. Paths are established in the bottom, middle and top of the freezing wall for single and double rows of the freezing tubes. Temperature distribution curves are plotted for each path. Significant conclusions can be drawn through observation of the patterns of freezing wall thickness changing with time. The results are useful for safe construction of tunnel connection aisles.

Key words: 3D finite element method, artificial freezing method, freezing wall, connection aisle

中图分类号: